100206, Tashkent, S. Azimov St., 74
To show on the map
Water supply, gas pipelines, sewerage, power cables, communication lines and more
Over 8 years of experience
Which allows us to carry out projects of any complexity
Team of professionals
They know all the nuances of the work and carry out the project with high quality
A complex approach
A full range of services for the implementation of your turnkey project
Own fleet of special equipment
This reduces both the cost and the timeline of your project
SPECSTROY carries out horizontal directional drilling and pipe jacking works. We have been operating since 2018, previously under the name BURSPETSMONTAZH. Our own fleet of drilling equipment, qualified crews, and experience on projects of national scale.
Our main focus is trenchless crossings for utility installation: water supply, gas pipelines, sewerage, power cables and fibre-optic lines. Diameters from 100 to 750 mm by HDD, and from 700 up to 2500 mm by pipe jacking.
Trenchless Pipe Installation
We install pipelines using the HDD method without opening the ground: diameters from 100 to 750 mm, up to 250 m in a single bore.
The method works where a trench is impossible or too costly — under live roads, pavements, landscaped areas and irrigation channels.
We work with both HDPE and steel pipes.
Site visit by our engineer and preliminary cost estimate are free of charge.
Controlled Crossing Under Railways and Roads
Trenchless crossing beneath a railway or motorway without interrupting traffic.
Diameters from 100 to 750 mm, lengths up to 250 m.
We carry out crossings under live tracks, including the Afrosiyob high-speed rail line.
The bore path is set and monitored by a locating system — drilling follows the design level and exits at the specified point. The road surface is not opened, the embankment stays intact, and we handle the crossing approvals ourselves.
Power Cable and Fibre-Optic Installation
Trenchless installation of power cables and fibre-optic communication lines — either inside an HDPE casing ⌀100–750 mm or by pulling the cable directly, without a casing.
In 2022 we installed around 1 km of PvPu cable (cross-linked polyethylene insulation) from HPP-1 around the Tashkent Zoo.
We work in dense urban areas where digging a trench is not an option.
Trenchless Gas Pipeline Installation
Gas pipeline installation by HDD — polyethylene (PE) or steel pipe, diameters from 100 to 750 mm, lengths up to 250 m. We comply with required burial depths and clearances to existing utilities.
Where necessary, we carry out test pits to determine the exact position of live networks along the route.
Trenchless Sewerage Installation
Gravity and pressure sewerage by HDD, diameters from 100 to 750 mm, lengths up to 250 m. For gravity sections we maintain the design gradient — the bore path is monitored along the entire length.
We work in confined conditions: inside courtyards, under existing driveways and across landscaped areas, without damaging the surface.
Water Supply Installation by HDD
Trenchless installation of water supply lines: HDPE or steel, diameters from 100 to 750 mm, lengths up to 250 m. Used for building connections, road crossings and street network installation.
No open excavation — paving and planting remain untouched, and no reinstatement works are needed afterwards.
HDD Design and Approvals
We prepare working drawings for the crossing: route, burial depth, bore profile, calculations based on diameter and soil conditions, and a bill of materials.
For works requiring a design licence, we engage a licensed design organisation — the client does not need to find one.
We also handle approvals with utility owners and road authorities.
HDPE Pipe Welding
Butt fusion welding of polyethylene pipes. Carried out both as part of HDD works and as a standalone service at the client’s site.
Welding is priced separately from drilling; the cost depends on diameter and number of joints — we will quote against your specification.
Pipe Jacking, Diameters from 700 to 2500 mm
Installation of steel casings by pipe jacking — diameters above 700 mm, with technical capability up to 2500 mm. The method is used where the diameter exceeds what HDD can handle: casings for trunk gas and oil pipelines, crossings under railways and roads, embankments and canals. Completed projects include a ⌀1420 mm crossing 53.4 m long and a ⌀1220 mm crossing under the Bukhara–Nukus highway. Traffic is not interrupted and the embankment is not opened.
Preliminary calculation of the project cost
{{ total }} сум
Price including VATВНИМАНИЕ расчёт является предварительным! В стоимость работ ГНБ не включены: сварка и стоимость труб, подготовка стартового и приёмного котлована, доставка спецтехники, а также шурфовка коммуникаций на объекте. Указанные цены ГНБ могут быть изменены в зависимости от общего объема работ, от длины и количества труб в одной скважине, от материала затягиваемых труб, от геологических свойств грунта и географии объекта.
We process the application
Call +998 71 233 3239 or message us on Telegram / WhatsApp: +998 90 359 1379, +998 99 822 6035
We prepare an estimate
We assess the scope and preliminary cost
We send a quotation
You receive a commercial offer with pricing and timelines
Site visit
Our engineer arrives within 24 hours
Estimate adjustment
We finalise the project cost and schedule
Contract signing
We sign the works agreement
Works commence
Drilling starts immediately after payment
Handover
On completion of the project
Completed projects
Pipeline installation by HDD, ADM Jizzakh, Jizzakh Region
Length:
406.5 mProject date:
03/02/2025Pipe diameter:
273–426 mm
Chupon-Ota Photovoltaic Plant, Samarkand — Enter Engineering
Length:
614 mProject date:
01/06/2023Pipe diameter:
160–200 mm
UTG (GTS) Trunk Pipeline Upgrade — Enter Engineering
Length:
53.4 mProject date:
01/09/2023Pipe diameter:
1420 mm
Crossing under the Bukhara–Nukus Highway
Length:
34 mProject date:
01/10/2018Pipe diameter:
1220 mmPhoto gallery